New Terminal C North Project

The new Terminal C North will be a new 265,000 sf two-level replacement facility. It will include 12 new gates and 60,000 sf of renovation work to the existing west connector in terminal C. The new facility construction is to the west of the existing IAH Terminal C North. Upon completion of the new project, United will vacate the existing Terminal C North. The Houston Airport System will demolish the existing terminal C to begin IAH Terminal D construction.Project team:
Program manager: Faithful+Gould
Designer: PGAL
Construction Manager at Risk (CMAR): Manhattan Construction

Procurement Schedule

Receive bid notices, event announcements, and project updates via email

Site demo and mobilization

DescriptionSelective site demolition of existing structures, paving, and underground utilities to facilitate construction of new UAL Terminal C North. Includes cut/cap/relocate/make safe of existing above-ground and underground utilities to facilitate demolition. Includes temporary construction fencing and construction barriers.
CMARManhattan Construction
ContactDamon Spinks
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)
All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.
Bidding InformationBid due date: March 6, 2015, Friday
Related eventsPre-Bid Meeting
Date: February 17, 2015
Time: 10:00 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsW-9 form
Bid clarification 2 (PDF)
Bid clarification 3 (PDF)
Pre-bid meeting sign-in sheet (PDF)
Pre-bid meeting presentation (PDF)
Bid clarifications 5 and 6 can be found on iSqFt, access number VQBM-2J6V

Foundation and Utilities

DescriptionSite utilities, foundations, and earthwork: the main project consists of a new 265,000 SF pier with 14 gates and 60,000 SF of renovation work to the existing west connector in Terminal C.
Project TeamManhattan Construction
ContactPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationBid due date: April 21, 2015, Tuesday
Related eventsPre-Bid Meeting
Date: April 2, 2015
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number 4X33-53V8
Pre-bid meeting sign-in sheet (PDF)
Pre-bid meeting presentation (PDF)
Bid clarification 1 (PDF)
Bid clarification 2 (PDF)
Bid clarification 3 (PDF)

MEPF design-assist

DescriptionPlumbing, HVAC, fire protection, and electrical design-assist: these scopes of work will be awarded on the basis of fee, fixed general conditions, and a scored interview.
Project TeamManhattan Construction
ContactMatt Hammer
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationBid due date: April 29, 2015, Wednesday
Related eventsPre-Bid Meeting
Date: April 14, 2015
Time: 8:30 a.m.
Location: United Airlines Project Management Office, 4975 Wright Road, Houston, TX 77032
DocumentsiSqFt access number NZHV-NRRC
Pre-bid meeting sign-in sheet (PDF)
Pre-bid meeting presentation (PowerPoint)
Addendum 1 (PDF)
Addendum 2 (PDF)
Addendum 3 (PDF)
Addendum 4 (PDF)

Steel and concrete

DescriptionThis is the elevated concrete and structural steel package for this project. We are seeking bids for turnkey concrete, formwork, place and finish, reinforcing steel material and erection, post-tension materials, structural steel fabrication & erection (turnkey).
Project TeamManhattan Construction
ContactMatt Hammer
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationBid due date: May 28, 2015, Wednesday
Related eventsPre-Bid Meeting
Date: May 19, 2015, Tuesday
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number X4W6-XHDF
Pre-bid meeting sign-in sheet (PDF)
Addendum 1 (PDF)
Addendum 2 (PDF)
Addendum 3 (PDF)
Addendum 4 (PDF)
Addendum 5 (PDF)

B-bus office buildout and general trades

DescriptionBuildout of existing B-bus terminal for construction office spaces: general trades package pricing is requested as well (i.e. dumpsters, temporary toilets, etc.)
Project TeamManhattan Construction
ContactDamon Spinks
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationBid due date: July 16, 2015, Thursday
Related eventsPre-Bid Meeting
Date: June 9, 2015
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number J6NR-YXC7
Pre-bid meeting sign-in sheet (PDF)
Pre-bid meeting presentation
Bid clarification 1 (PDF)
Bid clarification 2 (PDF)

Exterior envelope: core and shell

DescriptionWe are seeking bids for masonry, waterproofing, insulation, fireproofing, metal panels, roofing (membrane and standing seam metal), storefront and curtain walls, metal panels, stucco assemblies, louvers, elevators, fire protection, and site paving.
Project TeamManhattan Construction
ContactDamon Spinks
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationBid due date: July 2, 2015, Thursday
Related eventsPre-Bid Meeting
Date: June 24, 2015
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number MB87-FCT6

Pre-bid meeting sign-in sheet (PDF)
Bid Clarification #1
Bid Clarification #2
Bid Clarification #3

IT ductbank and fuel pipe

Description
CMARCMAR Manhattan Construction
ContactDamon Spinks or Perla Lane
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationIT ductbank construction material:
Proposal due date: February 19, 2015, Thursday

Fuel pipe construction material:
Proposal due date: February 12, 2015, Thursday

Related eventsIT Ductbank bidder pre-proposal meeting
Date: February 16, 2015, Monday
Time: 10:00 a.m.
Location: United Airlines Project Management Office, 2120 Montrose, Houston, TX 77006
DocumentsRFP invitation (PDF)
Pre-proposal meeting sign-in sheet (PDF)
Addendum 1 (PDF)
Addendum 2 (PDF)

T-point relocation

DescriptionSelective site demolition of existing structures, paving, and interior renovation to facilitate relocation of existing T-point to facilitate construction of new Terminal C North: includes new site lighting, new/relocated concrete traffic barriers, and restriping of VSRs.
CMARManhattan Construction
ContactDamon Spinks
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

All submissions should be sent to the attention of Cindy Baldwin at cbaldwin@manhattanconstruction.com, with the exception of the Financial Statement.

Bidding InformationBid due date : March 18, 2015, Wednesday
Related eventsPre-Bid Meeting
Date: March 5, 2015
Time: 10:00 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number 31HX-2TSQ
Pre-bid meeting sign-in sheet (PDF)
Pre-bid meeting presentation (PDF)
Bid clarification 1
Bid clarification 2
Bid clarification 3
Bid clarification 4

Interiors #1 (Drywall, doors, frames, & hardware, GSE fuel island, miscellaneous metals)

DescriptionWe are seeking subcontractor/supplier bids for Drywall, Door, Frame & Hardware, GSE Fuel Island, and Miscellaneous Metals.
CMARManhattan Construction
ContactDamon Spinks
Subcontractor requirementsPre-qualification instructions (PDF)
Subcontractor’s Minimum Insurance Requirements (PDF)
Sample Surety Commitment Letter (PDF)

Bidding InformationBid due date : August 25, 2015, Tuesday
Related eventsPre-Bid Meeting
Date: August 12, 2015
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number 6FC7-4M4T
Pre-bid meeting sign-in sheet (PDF)
Pre-Bid Meeting PowerPoint Presentation (PDF)
Bid Clarification 1 (PDF)
Bid Clarification 2 (PDF)
Bid Clarification 3 (PDF)
Bid Clarification 4 (PDF)
Bid Clarification 5 (PDF)
Bid Clarification 6 (PDF)
Bid Clarification 7 (PDF)

Interiors #2 (finishes & low voltage systems)

DescriptionWe are seeking subcontractor/supplier bids for finishes and low voltage systems
CMARManhattan Construction
ContactDamon Spinks
Subcontractor requirements
Bidding InformationBid due date : September 9, 2015, Tuesday
Related eventsPre-Bid Meeting
Date: August 27, 2015
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number VSPC-JPJD
Pre-Bid Presentation (PDF)
Pre-Bid Sign-In Sheets (PDF))
Bid Clarification 1 (PDF)
Bid Clarification 2 (PDF)
Bid Clarification 3 (PDF)
Bid Clarification 4 (PDF)
Bid Clarification 5 (PDF)
Bid Clarification 6 (PDF)
Bid Clarification 7 (PDF)
Bid Clarification 8 (PDF)
Bid Clarification 9 (PDF)

Signage Package

DescriptionWe are soliciting subcontractor/supplier bids for select trades on the United Airlines New Terminal C North Signage Package.
CMARManhattan Construction
ContactMark Behm
Subcontractor requirements
Bidding InformationBid due date : January 20, 2016, Wednesday
Related eventsPre-Bid Meeting
Date: January 7, 2016
Time: 9:30 a.m.
Location: Houston Airport System, 18600 Lee Road, Conference Room #113, Humble, Texas 77338
DocumentsiSqFt access number HRW2-MFQ6
Pre-bid Presentation
Bid Clarification 1 (PDF)
Bid Clarification 2 (PDF)
Bid Clarification 3 (PDF)

Test & Balance/Final Clean

DescriptionThis package is to procure Testing & Balancing and Final Cleaning for the new United Terminal C North. Project is underway at this time. Substantial Completion date is 3/1/17. Total square footage of project is 277,975.
CMARManhattan Construction
ContactDamon Spinks
Subcontractor requirements
Bidding InformationBid due date : February 24, 2016, Wednesday
Related eventsPre-Bid Meeting
Date: February 17, 2016
Time: 2:30 p.m.
Location: AGC of America, 3825 Dacoma Street, Houston, TX 77092
DocumentsiSqFt access number XQTB-R6PZ
Testing Presentation(PDF)
Testing Pre-Bid Sign in(PDF)
Bid Clarification 1 (PDF)
Bid Clarification 2 (PDF)
Bid Clarification 3 (PDF)

M/WBE progress

Our program goal is to ensure that certified minority- and women-owned businesses have the opportunity to compete to provide products and services within United’s extensive supply chain. United encourages all viable minority- and women-owned businesses to become part of our Supplier Diversity Initiative.

Professional Services

Construction Services